| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 01, 2025 | Assent Application Received |
| May 05, 2025 | Administrative Review for Completeness |
| May 07, 2025 | Bio Team Review for Completeness |
| May 07, 2025 | Project Manager |
| May 07, 2025 | Application Accepted |
| May 09, 2025 | 30 day Public Notice Issued |
| May 22, 2025 | HPHC Historical Preservation No Effect |
| May 28, 2025 | US Army Corps of Engineers Project Number received. |
| Jun 09, 2025 | Public Notice End Date |
| Aug 12, 2025 | Biologist Report |
| Aug 12, 2025 | Plans Received |
| Aug 19, 2025 | Typist for Processing |
| Aug 19, 2025 | Executive Sign Off |
| Aug 19, 2025 | Sent to Photo Copy |
| Aug 19, 2025 | Permit Approved |
| Aug 21, 2025 | Permit Mailed |
| Sep 09, 2025 | Commencement of Work Notice received |
| Sep 09, 2025 | Land Evidence Date |