| Action Date | Action Description |
|---|---|
| Jun 16, 2025 | Assent Application Received |
| Jun 23, 2025 | Administrative Review for Completeness |
| Jul 23, 2025 | Bio Team Review for Completeness |
| Jul 23, 2025 | Application Accepted |
| Jul 23, 2025 | Project Manager |
| Aug 14, 2025 | HPHC Historical Preservation No Effect |
| Aug 28, 2025 | Biologist Report |
| Sep 02, 2025 | Typist for Processing |
| Sep 02, 2025 | Executive Sign Off |
| Sep 02, 2025 | Sent to Photo Copy |
| Sep 02, 2025 | Permit Approved |
| Sep 02, 2025 | Dock Post-Construction Certification by Engineer Required. |
| Sep 08, 2025 | Permit Mailed |