| Action Date | Action Description |
|---|---|
| Jul 21, 2025 | Assent Application Received |
| Jul 23, 2025 | Administrative Review for Completeness |
| Jul 24, 2025 | Bio Team Review for Completeness |
| Jul 24, 2025 | Project Manager |
| Jul 24, 2025 | Application Accepted |
| Jul 31, 2025 | Biologist Report |
| Aug 14, 2025 | HPHC Historical Preservation No Effect |
| Aug 20, 2025 | Executive Sign Off |
| Aug 20, 2025 | Sent to Photo Copy |
| Aug 20, 2025 | Permit Approved |
| Aug 20, 2025 | Typist for Processing |
| Aug 21, 2025 | Permit Mailed |
| Sep 09, 2025 | Land Evidence Date |
| Sep 23, 2025 | Commencement of Work Notice received |