| Action Date | Action Description |
|---|---|
| Engineering Report | |
| Aug 04, 2025 | Assent Application Received |
| Aug 06, 2025 | Administrative Review for Completeness |
| Aug 06, 2025 | Bio Team Review for Completeness |
| Aug 20, 2025 | Deficient Application - Owner Notification Sent |
| Aug 20, 2025 | Eng Team Review for Completeness |
| Sep 08, 2025 | Deficient Application Picked Up |
| Sep 15, 2025 | Deficiency Response Received |
| Oct 06, 2025 | Eng Team Review for Completeness |
| Oct 06, 2025 | Application Accepted |
| Oct 17, 2025 | HPHC Historical Preservation No Effect |