| Action Date | Action Description |
|---|---|
| Jan 23, 1996 | Application Accepted |
| Jan 23, 1996 | Category A* (Docks) |
| Jan 25, 1996 | Biologist Report |
| Jan 26, 1996 | Permit Approved |
| Jan 26, 1996 | Land Evidence Date |
| Feb 15, 1996 | Land Evidence Date |
| Feb 11, 2002 | Modification Request |
| Mar 04, 2002 | Historical Preservation Approval Granted |
| Mar 12, 2002 | Correspondence Received |
| Apr 03, 2002 | 30 day Public Notice Issued |
| Apr 03, 2002 | 30 day Public Notice Issued |
| May 28, 2002 | Biologist Report |
| May 28, 2002 | Engineering Report |
| Jun 03, 2002 | Modification Approved |
| Jun 17, 2005 | Correspondence Mailed/Faxed/E-mailed |
| Jan 16, 2007 | Modification Request |
| Jan 17, 2007 | Administrative Review for Completeness |
| Jan 22, 2007 | Team Review for Completeness |
| Feb 19, 2007 | HPHC Historical Preservation No Effect |
| May 22, 2007 | 30 day Public Notice Issued |
| May 31, 2007 | Objections/Comments Received |
| Jun 22, 2007 | Public Notice End Date |
| Jul 12, 2007 | US Army Corps of Engineers Approval Received |
| Aug 09, 2007 | Biologist Report |
| Aug 10, 2007 | Typist for Processing |
| Aug 10, 2007 | Executive Sign Off |
| Aug 10, 2007 | Sent to Photo Copy |
| Aug 10, 2007 | Modification Approved |
| Aug 23, 2007 | Dock Meeting -- Approval |
| Apr 09, 2013 | Modification Request |
| Apr 10, 2013 | Administrative Review for Completeness |
| Apr 29, 2013 | Team Review for Completeness |
| Apr 29, 2013 | Team Review for Completeness |
| May 06, 2013 | HPHC Historical Preservation No Effect |
| May 17, 2013 | 30 day Public Notice Issued |
| Jun 17, 2013 | Public Notice End Date |
| Jun 21, 2013 | Biologist Report |
| Jun 21, 2013 | Engineering Report |
| Jun 27, 2013 | Typist for Processing |
| Jun 27, 2013 | Modification Approved |
| Jul 02, 2013 | Executive Sign Off |
| Jul 02, 2013 | Sent to Photo Copy |
| Jul 24, 2013 | Land Evidence Date |
| Aug 01, 2013 | US Army Corps of Engineers Approval Received |