| Action Date | Action Description |
|---|---|
| May 14, 2004 | Application Accepted |
| Jun 08, 2004 | Historical Preservation Approval Granted |
| Feb 07, 2005 | Additional Information Received |
| Feb 28, 2005 | Category A assigned |
| Apr 01, 2005 | Plans Received |
| Apr 07, 2005 | Typist for Processing |
| Apr 07, 2005 | Executive Sign Off |
| Apr 07, 2005 | Sent to Photo Copy |
| Apr 07, 2005 | Permit Approved |
| Apr 19, 2005 | Land Evidence Date |
| Jun 24, 2005 | Modification Request |
| Jun 27, 2005 | Administrative Review for Completeness |
| Jun 27, 2005 | Team Review for Completeness |
| Jul 18, 2005 | Engineering Report |
| Jul 18, 2005 | Typist for Processing |
| Jul 18, 2005 | Executive Sign Off |
| Jul 18, 2005 | Sent to Photo Copy |
| Jul 18, 2005 | Modification Approved |
| Aug 26, 2005 | Land Evidence Date |
| Nov 29, 2005 | Modification Request |
| Nov 29, 2005 | Team Review for Completeness |
| Nov 30, 2005 | Engineering Report |
| Dec 07, 2005 | Typist for Processing |
| Dec 07, 2005 | Executive Sign Off |
| Dec 07, 2005 | Sent to Photo Copy |
| Dec 07, 2005 | Modification Approved |
| Dec 13, 2005 | HPHC Historical Preservation No Effect |
| Dec 20, 2005 | Land Evidence Date |
| Mar 16, 2006 | Modification Request |
| Mar 17, 2006 | Administrative Review for Completeness |
| Mar 20, 2006 | Team Review for Completeness |
| Mar 21, 2006 | Biologist Report |
| Mar 21, 2006 | Engineering Report |
| Mar 21, 2006 | Typist for Processing |
| Mar 21, 2006 | Modification Approved |
| Mar 22, 2006 | Executive Sign Off |
| Mar 22, 2006 | Sent to Photo Copy |
| Mar 24, 2006 | HPHC Historical Preservation No Effect |
| Apr 13, 2006 | Land Evidence Date |