| Action Date | Action Description |
|---|---|
| Aug 15, 2005 | Assent Application Received |
| Aug 15, 2005 | Correspondence Mailed/Faxed/E-mailed |
| Aug 16, 2005 | Administrative Review for Completeness |
| Aug 19, 2005 | Team Review for Completeness |
| Aug 19, 2005 | Application Accepted |
| Aug 19, 2005 | Category B assigned |
| Sep 06, 2005 | HPHC Review Pending |
| Sep 07, 2005 | 30 day Public Notice Issued |
| Oct 04, 2005 | Biologist Report |
| Oct 04, 2005 | Engineering Report |
| Oct 07, 2005 | Public Notice End Date |
| Oct 07, 2005 | Executive Sign Off |
| Oct 17, 2005 | Correspondence Received |
| Oct 19, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Oct 19, 2005 | Mail Agenda Notice |
| Oct 25, 2005 | Semi-Monthly Meeting Date Scheduled |
| Oct 25, 2005 | Semi-Monthly Meeting Held |
| Oct 25, 2005 | Council Approval Granted |
| Nov 08, 2005 | Stipulation Package from Biologist |
| Nov 08, 2005 | Stipulation Package by Engineer |
| Nov 09, 2005 | Typist for Processing |
| Nov 09, 2005 | Executive Sign Off |
| Nov 09, 2005 | Sent to Photo Copy |
| Nov 09, 2005 | Permit Approved |
| Nov 29, 2005 | Legal Response/Decision |
| Dec 02, 2005 | Under Review/Decision |
| Jan 23, 2006 | Land Evidence Date |
| Jan 24, 2006 | Commencement of Work Notice received |