| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Sep 26, 2005 | Assent Application Received |
| Sep 27, 2005 | Administrative Review for Completeness |
| Oct 11, 2005 | Deficient Application - Owner Notification Sent |
| Nov 04, 2005 | Phone Call |
| Nov 22, 2005 | Deficiency Response Received |
| Nov 30, 2005 | Team Review for Completeness |
| Nov 30, 2005 | Application Accepted |
| Nov 30, 2005 | Category B assigned |
| Dec 05, 2005 | 30 day Public Notice Issued |
| Dec 13, 2005 | HPHC Historical Preservation No Effect |
| Jan 05, 2006 | Public Notice End Date |
| Jan 10, 2006 | Engineering Report |
| Jan 12, 2006 | Biologist Review not required |
| Jan 12, 2006 | Supervisor Engineer SignOff |
| Jan 12, 2006 | Executive Sign Off |
| Feb 06, 2006 | US Army Corp of Engineers Permit Date |
| Feb 07, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Feb 07, 2006 | Mail Agenda Notice |
| Feb 08, 2006 | US Army Corps of Engineers Approval Received |
| Feb 14, 2006 | Semi-Monthly Meeting Unexcused Absence |
| Feb 14, 2006 | Semi-Monthly Meeting Date Scheduled |
| Feb 16, 2006 | Mail Agenda Notice |
| Feb 28, 2006 | Semi-Monthly Meeting Held |
| Feb 28, 2006 | Council Approval Granted |
| Feb 28, 2006 | Semi-Monthly Meeting Date Scheduled |
| Apr 25, 2006 | Stipulation Package from Biologist |
| Apr 25, 2006 | Stipulation Package by Engineer |
| Apr 26, 2006 | Typist for Processing |
| Apr 26, 2006 | Executive Sign Off |
| Apr 26, 2006 | Sent to Photo Copy |
| Apr 26, 2006 | Permit Approved |
| May 17, 2006 | Land Evidence Date |