| Action Date | Action Description |
|---|---|
| Dec 27, 2005 | Assent Application Received |
| Dec 28, 2005 | Administrative Review for Completeness |
| Dec 28, 2005 | Team Review for Completeness |
| Dec 28, 2005 | Application Accepted |
| Jan 03, 2006 | 30 day Public Notice Issued |
| Jan 10, 2006 | HPHC Historical Preservation No Effect |
| Feb 03, 2006 | Public Notice End Date |
| Nov 14, 2006 | Additional Information Requested from Applicant |
| Apr 11, 2008 | Plans Received |
| Dec 04, 2008 | Additional Information Received |
| Dec 22, 2008 | Plans Received |
| Feb 26, 2009 | Typist for Processing |
| Feb 26, 2009 | Executive Sign Off |
| Feb 26, 2009 | Sent to Photo Copy |
| Feb 26, 2009 | Permit Approved |
| Feb 26, 2009 | Biologist Report |
| Feb 26, 2009 | Engineering Report |
| Mar 04, 2009 | Land Evidence Date |