| Action Date | Action Description |
|---|---|
| Feb 17, 2009 | Assent Application Received |
| Feb 18, 2009 | Administrative Review for Completeness |
| Mar 05, 2009 | Team Review for Completeness |
| Mar 05, 2009 | Team Review for Completeness |
| Mar 05, 2009 | Application Accepted |
| Mar 31, 2009 | HPHC Historical Preservation No Effect |
| Apr 03, 2009 | Plans Received |
| Apr 09, 2009 | 30 day Public Notice Issued |
| May 09, 2009 | Public Notice End Date |
| May 15, 2009 | Engineering Report |
| May 28, 2009 | Biologist Report |
| May 28, 2009 | Scheduled for Section 110 Review meeting |
| May 28, 2009 | Typist for Processing |
| May 28, 2009 | Dock/1.1.6 Review approval |
| May 28, 2009 | Executive Sign Off |
| May 28, 2009 | Sent to Photo Copy |
| May 28, 2009 | Permit Approved |
| Jul 13, 2009 | Land Evidence Date |
| Sep 09, 2009 | Commencement of Work Notice received |