| Action Date | Action Description |
|---|---|
| Dec 09, 2009 | Assent Application Received |
| Dec 10, 2009 | Administrative Review for Completeness |
| Dec 28, 2009 | Team Review for Completeness |
| Dec 28, 2009 | Team Review for Completeness |
| Jan 08, 2010 | Application Accepted |
| Jan 20, 2010 | Biologist Report |
| Jan 20, 2010 | Engineering Report |
| Jan 20, 2010 | Typist for Processing |
| Jan 20, 2010 | Executive Sign Off |
| Jan 20, 2010 | Sent to Photo Copy |
| Jan 20, 2010 | Permit Approved |
| Jan 22, 2010 | HPHC Historical Preservation No Effect |
| Feb 16, 2010 | Land Evidence Date |