| Action Date | Action Description |
|---|---|
| Apr 13, 2010 | Assent Application Received |
| Apr 14, 2010 | Administrative Review for Completeness |
| Apr 30, 2010 | Team Review for Completeness |
| Apr 30, 2010 | Team Review for Completeness |
| Apr 30, 2010 | Application Accepted |
| May 10, 2010 | HPHC Historical Preservation No Effect |
| Jun 08, 2010 | 30 day Public Notice Issued |
| Jun 28, 2010 | Objections/Comments Received |
| Jul 08, 2010 | Public Notice End Date |
| Jul 20, 2010 | US Army Corp of Engineers Permit Date |
| Jul 23, 2010 | US Army Corps of Engineers Approval Received |
| Jul 29, 2010 | Supervisor Engineer SignOff |
| Jul 29, 2010 | Supervisor Biologist SignOff |
| Jul 29, 2010 | Biologist Report |
| Jul 29, 2010 | Engineering Report |
| Aug 06, 2010 | Executive Signoff of Staff Reports |
| Aug 27, 2010 | Water Quality Certification |
| Aug 27, 2010 | Water Quality Certification |
| Aug 31, 2010 | Ready to Schedule Semi-Monthly Meeting |
| Sep 01, 2010 | Mail Agenda Notice |
| Sep 28, 2010 | Semi-Monthly Meeting Date Scheduled |
| Oct 07, 2010 | Mail Agenda Notice |
| Oct 12, 2010 | Semi-Monthly Meeting Held |
| Oct 12, 2010 | Council Approval Granted |
| Oct 13, 2010 | Semi-Monthly Meeting Date Scheduled |
| Oct 26, 2010 | Legal Response/Decision |
| Nov 12, 2010 | Typist for Processing |
| Nov 12, 2010 | Stipulation Package from Biologist |
| Nov 12, 2010 | Stipulation Package by Engineer |
| Nov 12, 2010 | Permit Approved |
| Nov 17, 2010 | Executive Sign Off |
| Nov 17, 2010 | Sent to Photo Copy |
| Nov 19, 2010 | Land Evidence Date |
| May 09, 2011 | Commencement of Work Notice received |