| Action Date | Action Description |
|---|---|
| Sep 29, 2010 | Assent Application Received |
| Oct 01, 2010 | Administrative Review for Completeness |
| Oct 01, 2010 | Team Review for Completeness |
| Oct 01, 2010 | Team Review for Completeness |
| Oct 01, 2010 | Application Accepted |
| Oct 12, 2010 | Engineering Report |
| Oct 14, 2010 | Typist for Processing |
| Oct 14, 2010 | Biologist Report |
| Oct 15, 2010 | Permit Approved |
| Oct 18, 2010 | Executive Sign Off |
| Oct 18, 2010 | Sent to Photo Copy |
| Nov 10, 2010 | Land Evidence Date |
| Nov 16, 2010 | HPHC Historical Preservation No Effect |
| Dec 10, 2010 | Modification Request |
| Dec 15, 2010 | Administrative Review for Completeness |
| Dec 15, 2010 | Team Review for Completeness |
| Dec 15, 2010 | Team Review for Completeness |
| Dec 16, 2010 | Biologist Report |
| Dec 16, 2010 | Engineering Report |
| Dec 16, 2010 | Modification Approved |
| Dec 17, 2010 | Land Evidence Date |
| Jan 07, 2011 | HPHC Historical Preservation No Effect |