| Action Date | Action Description |
|---|---|
| Nov 23, 2010 | Assent Application Received |
| Nov 24, 2010 | Administrative Review for Completeness |
| Nov 29, 2010 | Team Review for Completeness |
| Nov 29, 2010 | Team Review for Completeness |
| Nov 29, 2010 | Application Accepted |
| Dec 08, 2010 | HPHC Historical Preservation No Effect |
| Dec 15, 2010 | 30 day Public Notice Issued |
| Jan 31, 2011 | Public Notice End Date Extension Granted |
| Feb 01, 2011 | Biologist Report |
| Feb 01, 2011 | Engineering Report |
| Feb 03, 2011 | Supervisor Engineer SignOff |
| Feb 03, 2011 | Supervisor Biologist SignOff |
| Feb 03, 2011 | Executive Signoff of Staff Reports |
| Feb 08, 2011 | Correspondence Received |
| Mar 02, 2011 | Ready to Schedule Semi-Monthly Meeting |
| Mar 02, 2011 | Mail Agenda Notice |
| Mar 08, 2011 | Council Approval Granted |
| Mar 08, 2011 | Semi-Monthly Meeting Date Scheduled |
| Mar 08, 2011 | Semi-Monthly Meeting Held |
| Apr 13, 2011 | Legal Response/Decision |
| Apr 18, 2011 | Permit Approved |
| Apr 18, 2011 | Typist for Processing |
| Apr 18, 2011 | Stipulation Package from Biologist |
| Apr 18, 2011 | Stipulation Package by Engineer |
| Apr 21, 2011 | Executive Sign Off |
| Apr 21, 2011 | Sent to Photo Copy |
| Jun 23, 2011 | Land Evidence Date |