| Action Date | Action Description |
|---|---|
| Feb 16, 2011 | Assent Application Received |
| Feb 16, 2011 | Administrative Review for Completeness |
| Feb 22, 2011 | Team Review for Completeness |
| Feb 22, 2011 | Team Review for Completeness |
| Feb 22, 2011 | Application Accepted |
| Mar 15, 2011 | Biologist Report |
| Mar 15, 2011 | Engineering Report |
| Mar 16, 2011 | Typist for Processing |
| Mar 16, 2011 | Permit Approved |
| Mar 17, 2011 | HPHC Historical Preservation No Effect |
| Mar 17, 2011 | Executive Sign Off |
| Mar 17, 2011 | Sent to Photo Copy |
| Mar 21, 2011 | Land Evidence Date |
| Apr 06, 2011 | Commencement of Work Notice received |