| Action Date | Action Description |
|---|---|
| Sep 13, 2011 | Assent Application Received |
| Sep 14, 2011 | Administrative Review for Completeness |
| Sep 19, 2011 | Team Review for Completeness |
| Sep 19, 2011 | Application Accepted |
| Sep 28, 2011 | HPHC Historical Preservation No Effect |
| Sep 30, 2011 | 30 day Public Notice Issued |
| Oct 04, 2011 | Biologist Report |
| Oct 21, 2011 | Correspondence Received |
| Oct 24, 2011 | Correspondence Mailed/Faxed/E-mailed |
| Oct 28, 2011 | Public Notice End Date |
| Nov 07, 2011 | Engineering Report |
| Nov 09, 2011 | Typist for Processing |
| Nov 09, 2011 | Permit Approved |
| Nov 14, 2011 | Executive Sign Off |
| Nov 14, 2011 | Sent to Photo Copy |
| Nov 17, 2011 | US Army Corps of Engineers Approval Received |
| Nov 21, 2011 | Land Evidence Date |