| Action Date | Action Description |
|---|---|
| Nov 21, 2011 | Assent Application Received |
| Nov 23, 2011 | Administrative Review for Completeness |
| Nov 28, 2011 | Team Review for Completeness |
| Nov 28, 2011 | Team Review for Completeness |
| Nov 28, 2011 | Application Accepted |
| Dec 07, 2011 | Biologist Report |
| Dec 07, 2011 | Engineering Report |
| Dec 07, 2011 | Additional Information Received |
| Dec 09, 2011 | Typist for Processing |
| Dec 09, 2011 | Permit Approved |
| Dec 12, 2011 | Executive Sign Off |
| Dec 12, 2011 | Sent to Photo Copy |
| Jan 12, 2012 | HPHC Historical Preservation Comments/Concerns |
| Jan 13, 2012 | US Army Corps of Engineers Approval Received |
| Feb 07, 2012 | Modification Request |
| Feb 07, 2012 | Administrative Review for Completeness |
| Feb 07, 2012 | Team Review for Completeness |
| Feb 13, 2012 | Engineering Report |
| Feb 14, 2012 | Modification Approved |
| Feb 14, 2012 | Typist for Processing |
| Feb 15, 2012 | Executive Sign Off |
| Feb 15, 2012 | Sent to Photo Copy |
| Feb 17, 2012 | Certified Receipt Received |
| Mar 12, 2012 | Land Evidence Date |
| Mar 12, 2012 | Land Evidence Date |
| Jun 20, 2012 | US Army Corps of Engineers Approval Received |