| Action Date | Action Description |
|---|---|
| Feb 07, 2012 | Assent Application Received |
| Feb 07, 2012 | Administrative Review for Completeness |
| Feb 09, 2012 | Team Review for Completeness |
| Feb 09, 2012 | Team Review for Completeness |
| Feb 09, 2012 | Application Accepted |
| Feb 24, 2012 | Plans Received |
| Mar 06, 2012 | HPHC Historical Preservation No Effect |
| Apr 12, 2012 | Plans Received |
| Apr 16, 2012 | Typist for Processing |
| Apr 16, 2012 | Biologist Report |
| Apr 16, 2012 | Engineering Report |
| Apr 16, 2012 | Permit Approved |
| Apr 17, 2012 | Plans Received |
| Apr 17, 2012 | Executive Sign Off |
| Apr 17, 2012 | Sent to Photo Copy |