| Action Date | Action Description |
|---|---|
| Jul 19, 2012 | Assent Application Received |
| Jul 19, 2012 | Administrative Review for Completeness |
| Jul 19, 2012 | Team Review for Completeness |
| Jul 19, 2012 | Team Review for Completeness |
| Jul 19, 2012 | Application Accepted |
| Jul 24, 2012 | 30 day Public Notice Issued |
| Aug 24, 2012 | Public Notice End Date |
| Aug 27, 2012 | HPHC Historical Preservation No Effect |
| Sep 08, 2012 | HPHC Historical Preservation No Effect |
| Sep 12, 2012 | Correspondence Received |
| Sep 19, 2012 | Biologist Report |
| Sep 19, 2012 | Engineering Report |
| Sep 19, 2012 | Supervisor Engineer SignOff |
| Sep 19, 2012 | Special Exception Public Hearing Notice mailed |
| Sep 20, 2012 | Supervisor Biologist SignOff |
| Sep 20, 2012 | Executive Signoff of Staff Reports |
| Oct 23, 2012 | Council Approval Granted |
| Oct 23, 2012 | Semi-Monthly Meeting Date Scheduled |
| Nov 23, 2012 | US Army Corps of Engineers Approval Received |
| Nov 29, 2012 | Typist for Processing |
| Nov 29, 2012 | Stipulation Package from Biologist |
| Nov 29, 2012 | Stipulation Package by Engineer |
| Nov 29, 2012 | Legal Response/Decision |
| Nov 29, 2012 | Permit Approved |
| Nov 30, 2012 | Executive Sign Off |
| Nov 30, 2012 | Sent to Photo Copy |