| Action Date | Action Description |
|---|---|
| Mar 27, 2013 | Maintenance Certification Request |
| Mar 27, 2013 | Administrative Review for Completeness |
| Mar 28, 2013 | Team Review for Completeness |
| Mar 28, 2013 | Application Accepted |
| Apr 05, 2013 | HPHC Historical Preservation No Effect |
| Apr 15, 2013 | Additional Information Received |
| May 15, 2013 | Biologist Report |
| May 15, 2013 | Engineering Report |
| May 17, 2013 | Typist for Processing |
| May 17, 2013 | Permit Approved |
| May 20, 2013 | Executive Sign Off |
| May 20, 2013 | Sent to Photo Copy |