| Action Date | Action Description |
|---|---|
| Sep 25, 2013 | Assent Application Received |
| Sep 27, 2013 | Administrative Review for Completeness |
| Sep 27, 2013 | Team Review for Completeness |
| Oct 04, 2013 | Deficient Application - Owner Notification Sent |
| Dec 26, 2013 | Plans Received |
| Dec 26, 2013 | Correspondence Received |
| Dec 26, 2013 | Deficiency Response Received |
| Dec 26, 2013 | Team Review for Completeness |
| Dec 26, 2013 | Application Accepted |
| Jan 09, 2014 | 30 day Public Notice Issued |
| Feb 09, 2014 | Public Notice End Date |
| Mar 14, 2014 | Additional Information Received |
| Mar 27, 2014 | Biologist Report |
| Apr 07, 2014 | US Army Corps of Engineers Approval Received |
| Apr 11, 2014 | Supervisor Biologist SignOff |
| Apr 14, 2014 | Supervisor Engineer SignOff |
| Apr 14, 2014 | Executive Signoff of Staff Reports |
| May 01, 2014 | Special Exception Public Hearing Notice mailed |
| May 07, 2014 | Entry of Appearance Received |
| Jun 24, 2014 | Council Approval Granted |
| Jun 24, 2014 | Semi-Monthly Meeting Date Scheduled |
| Jun 24, 2014 | Semi-Monthly Meeting Held |
| Jul 23, 2014 | 30 Day Appeal Notification to Owner |
| Jul 23, 2014 | Legal Response/Decision |
| Jul 30, 2014 | Stipulation Package from Biologist |
| Jul 31, 2014 | Permit Approved |
| Jul 31, 2014 | Typist for Processing |
| Aug 01, 2014 | Executive Sign Off |
| Aug 01, 2014 | Sent to Photo Copy |
| Aug 12, 2014 | Land Evidence Date |