| Action Date | Action Description |
|---|---|
| Jun 02, 2014 | Assent Application Received |
| Jun 03, 2014 | Administrative Review for Completeness |
| Jun 03, 2014 | Team Review for Completeness |
| Jun 03, 2014 | Application Accepted |
| Jun 10, 2014 | HPHC Historical Preservation No Effect |
| Jul 01, 2014 | 30 day Public Notice Issued |
| Jul 15, 2014 | Objections/Comments Received |
| Jul 21, 2014 | Objections/Comments Received |
| Jul 31, 2014 | Public Notice End Date Extension Granted |
| Aug 01, 2014 | Public Notice End Date |
| Aug 12, 2014 | Public Notice End Date |
| Sep 10, 2014 | Additional Information Requested from Applicant |
| Oct 31, 2014 | Plans Received |
| Nov 07, 2014 | 30 day Public Notice Issued |
| Nov 21, 2014 | Objections/Comments Received |
| Dec 02, 2014 | Objections/Comments Received |
| Dec 03, 2014 | Objections/Comments Received |
| Jan 02, 2015 | Objections/Comments Received |
| Feb 10, 2015 | Correspondence Received |
| Feb 17, 2015 | Objection withdrawal received |
| Feb 20, 2015 | Plans Received |
| Feb 05, 2016 | Plans Received |
| Mar 21, 2016 | Plans Received |
| Mar 22, 2016 | Engineering Report |
| Mar 22, 2016 | Supervisor Biologist SignOff |
| Mar 22, 2016 | Supervisor Engineer SignOff |
| Mar 22, 2016 | Executive Signoff of Staff Reports |
| Mar 22, 2016 | Biologist Report |
| Apr 26, 2016 | Ready to Schedule Semi-Monthly Meeting |
| Apr 26, 2016 | Mail Agenda Notice |
| May 10, 2016 | Council Approval Granted |
| May 10, 2016 | Semi-Monthly Meeting Date Scheduled |
| Jun 06, 2016 | Legal Response/Decision |
| Jun 06, 2016 | 30 Day Appeal Notification to Owner |
| Jul 11, 2016 | Category A* (Docks) |
| Jul 11, 2016 | Stipulation Package from Biologist |
| Jul 13, 2016 | Permit Approved |
| Jul 13, 2016 | Typist for Processing |
| Jul 13, 2016 | Executive Sign Off |
| Jul 13, 2016 | Sent to Photo Copy |
| Jul 18, 2016 | Land Evidence Date |