| Action Date | Action Description |
|---|---|
| Aug 04, 2014 | Assent Application Received |
| Aug 05, 2014 | Administrative Review for Completeness |
| Aug 12, 2014 | Team Review for Completeness |
| Aug 12, 2014 | Deficient Application - Owner Notification Sent |
| Aug 13, 2014 | HPHC Historical Preservation No Effect |
| Aug 20, 2014 | Plans Received |
| Sep 02, 2014 | Deficient Application Picked Up |
| Oct 15, 2014 | Deficiency Response Received |
| Oct 24, 2014 | Team Review for Completeness |
| Oct 24, 2014 | Application Accepted |
| Nov 25, 2014 | 30 day Public Notice Issued |
| Dec 26, 2014 | Public Notice End Date |
| Dec 31, 2014 | Biologist Report |
| Jan 12, 2015 | Typist for Processing |
| Jan 12, 2015 | Permit Approved |
| Jan 14, 2015 | Executive Sign Off |
| Jan 14, 2015 | Sent to Photo Copy |
| Jan 20, 2015 | Land Evidence Date |
| Jan 30, 2015 | US Army Corps of Engineers Approval Received |
| Feb 20, 2015 | Enforcement Review of application for compliance |
| Feb 20, 2015 | Correspondence Mailed/Faxed/E-mailed |