| Action Date | Action Description |
|---|---|
| Aug 20, 2015 | Assent Application Received |
| Aug 21, 2015 | Administrative Review for Completeness |
| Aug 21, 2015 | Team Review for Completeness |
| Aug 21, 2015 | Application Accepted |
| Sep 02, 2015 | HPHC Historical Preservation No Effect |
| Oct 06, 2015 | Additional Information Requested from Applicant |
| Jan 28, 2016 | Additional Information Received |
| Feb 11, 2016 | Plans Received |
| Feb 11, 2016 | Biologist Report |
| Feb 12, 2016 | Typist for Processing |
| Feb 15, 2016 | Executive Sign Off |
| Feb 15, 2016 | Sent to Photo Copy |
| Feb 15, 2016 | Permit Approved |
| Feb 26, 2016 | Land Evidence Date |