| Action Date | Action Description |
|---|---|
| Jun 01, 2016 | Assent Application Received |
| Jun 02, 2016 | Administrative Review for Completeness |
| Aug 09, 2016 | Team Review for Completeness |
| Aug 09, 2016 | Plans Received |
| Aug 09, 2016 | Application Accepted |
| Aug 24, 2016 | Engineering Report |
| Aug 25, 2016 | Typist for Processing |
| Aug 25, 2016 | Executive Sign Off |
| Aug 25, 2016 | Permit Approved |
| Sep 02, 2016 | Land Evidence Date |
| Dec 06, 2016 | HPHC Historical Preservation No Effect |