| Action Date | Action Description |
|---|---|
| Jan 03, 2017 | Aquaculture Application Received |
| Jan 04, 2017 | Aquaculture Administrative Review |
| Jan 04, 2017 | Application Accepted |
| Jan 04, 2017 | Category B assigned |
| Jan 06, 2017 | 30 day Public Notice Issued |
| Jan 13, 2017 | HPHC Historical Preservation No Effect |
| Feb 06, 2017 | Public Notice End Date |
| Feb 15, 2017 | Objections/Comments Received |
| Aug 18, 2017 | Objection withdrawal received |
| Aug 21, 2017 | Aquaculture Report |
| Aug 22, 2017 | Executive Signoff of Staff Reports |
| Oct 05, 2017 | Ready to Schedule Semi-Monthly Meeting |
| Dec 13, 2017 | Mail Agenda Notice |
| Jan 09, 2018 | Council Approval Granted |
| Jan 09, 2018 | Semi-Monthly Meeting Date Scheduled |
| Jan 29, 2018 | Legal Response/Decision |
| Feb 06, 2018 | Stipulation Package from Aquaculture Coordinator |
| Feb 07, 2018 | Typist for Processing |
| Feb 07, 2018 | Executive Sign Off |
| Feb 07, 2018 | Sent to Photo Copy |
| Feb 07, 2018 | Permit Approved |
| Feb 07, 2018 | Aquaculture Lease Cover Letter sent |
| Feb 07, 2018 | Aquaculture Lease Mailed |
| Feb 20, 2018 | Aquaculture Lease Received |
| Feb 20, 2018 | Aquaculture Lease Payment |
| Dec 03, 2018 | Aquaculture Lease Cover Letter sent |
| Jan 11, 2019 | Aquaculture Yearly Questionnaire |
| Jan 11, 2019 | Aquaculture Lease Payment |
| Dec 10, 2019 | Aquaculture Lease Cover Letter sent |
| Jan 13, 2020 | Aquaculture Yearly Questionnaire |
| Jan 13, 2020 | Aquaculture Lease Payment |
| Dec 22, 2020 | Aquaculture Lease Cover Letter sent |
| May 12, 2021 | Aquaculture Lease Payment |
| Dec 28, 2021 | Aquaculture Lease Cover Letter sent |
| Mar 01, 2022 | Aquaculture Yearly Questionnaire |
| Mar 01, 2022 | Aquaculture Lease Payment |
| Jun 27, 2022 | Extension of Permit Request |
| Aug 16, 2022 | Enforcement Compliance Inspection Required |
| Aug 16, 2022 | Process Extension |
| Aug 17, 2022 | Aquaculture Assent Renewal |
| Jan 17, 2023 | Aquaculture Lease Payment |
| Jan 17, 2023 | Aquaculture Yearly Questionnaire |
| Jun 15, 2023 | Modification Request |
| Jun 20, 2023 | Administrative Review for Completeness |
| Dec 19, 2023 | Aquaculture Administrative Review |
| Aug 01, 2024 | Correspondence Received |
| Aug 05, 2024 | Aquaculture Report |
| Aug 05, 2024 | Modification Approved |
| Aug 05, 2024 | Modification mailed |