| Action Date | Action Description |
|---|---|
| Jul 26, 2017 | Assent Application Received |
| Jul 27, 2017 | Administrative Review for Completeness |
| Jul 28, 2017 | Team Review for Completeness |
| Jul 28, 2017 | Application Accepted |
| Jul 31, 2017 | Plans Received |
| Aug 16, 2017 | HPHC Historical Preservation No Effect |
| Aug 31, 2017 | Public Notice End Date |
| Sep 15, 2017 | Biologist Report |
| Sep 15, 2017 | Engineering Report |
| Sep 20, 2017 | Plans Received |
| Sep 26, 2017 | Mail Agenda Notice |
| Oct 10, 2017 | Council Approval Granted |
| Oct 10, 2017 | Semi-Monthly Meeting Date Scheduled |
| Oct 12, 2017 | Legal Response/Decision |
| Oct 16, 2017 | Typist for Processing |
| Oct 16, 2017 | Stipulation Package from Biologist |
| Oct 16, 2017 | Stipulation Package by Engineer |
| Oct 17, 2017 | Executive Sign Off |
| Oct 17, 2017 | Sent to Photo Copy |
| Oct 17, 2017 | Permit Approved |
| Oct 27, 2017 | Land Evidence Date |
| Nov 27, 2017 | US Army Corps of Engineers Approval Received |
| Jan 05, 2018 | Modification Request |
| Jan 05, 2018 | Application Accepted |
| Jan 08, 2018 | Biologist Report |
| Jan 08, 2018 | Typist for Processing |
| Jan 08, 2018 | Executive Sign Off |
| Jan 08, 2018 | Sent to Photo Copy |
| Jan 08, 2018 | Modification Approved |