| Action Date | Action Description |
|---|---|
| Oct 19, 2017 | Dredge Application |
| Oct 20, 2017 | Administrative Review for Completeness |
| Oct 25, 2017 | Team Review for Completeness |
| Oct 25, 2017 | Application Accepted |
| Nov 02, 2017 | HPHC Historical Preservation No Effect |
| Nov 20, 2017 | Engineering Report |
| Nov 22, 2017 | Typist for Processing |
| Nov 22, 2017 | Executive Sign Off |
| Nov 22, 2017 | Sent to Photo Copy |
| Nov 22, 2017 | Permit Approved |
| Dec 08, 2017 | DEM Dredge Permit |
| Jan 10, 2018 | Duplicate Original Assent requested/mailed |
| Jan 11, 2018 | Land Evidence Date |
| Feb 26, 2018 | CAD Cell Fee Due - initial (letter) |
| May 07, 2018 | Correspondence Mailed/Faxed/E-mailed |
| Jun 06, 2018 | Correspondence Mailed/Faxed/E-mailed |
| Jun 13, 2018 | Additional Information Received |
| Aug 27, 2018 | CAD Cell Fee Due-Final |
| Aug 28, 2018 | Semi-Monthly Meeting Date Scheduled |