| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 06, 2017 | Assent Application Received |
| Nov 06, 2017 | Administrative Review for Completeness |
| Nov 07, 2017 | Team Review for Completeness |
| Nov 07, 2017 | Application Accepted |
| Nov 07, 2017 | Category A* (Docks) |
| Dec 01, 2017 | 30 day Public Notice Issued |
| Jan 01, 2018 | Public Notice End Date |
| Feb 21, 2018 | Additional Information Received |
| Apr 05, 2018 | Objections/Comments Received |
| Jun 18, 2018 | Additional Information Received |
| Jun 21, 2018 | HPHC Historical Preservation No Effect |
| Jul 06, 2018 | Engineering Report |
| Jul 09, 2018 | Permit Approved |
| Jul 09, 2018 | Typist for Processing |
| Jul 09, 2018 | Executive Sign Off |
| Jul 09, 2018 | Sent to Photo Copy |
| Aug 01, 2018 | Land Evidence Date |