| Action Date | Action Description |
|---|---|
| Mar 17, 2020 | Freshwater Wetland - Edge Verification Request |
| Mar 20, 2020 | Administrative Review for Completeness |
| Mar 30, 2020 | Bio Team Review for Completeness |
| Mar 30, 2020 | Project Manager |
| Mar 30, 2020 | Application Accepted |
| Apr 27, 2020 | HPHC Historical Preservation No Effect |
| Apr 27, 2020 | HPHC Review Pending |
| May 20, 2020 | Biologist Report |
| May 20, 2020 | Biologist Report |
| May 21, 2020 | Typist for Processing |
| May 21, 2020 | Executive Sign Off |
| May 21, 2020 | Sent to Photo Copy |
| May 21, 2020 | Freshwater Wetland Edge Verified |
| Jun 09, 2020 | Correspondence Received |
| Jul 08, 2020 | Correspondence Mailed/Faxed/E-mailed |
| Jul 10, 2020 | Correspondence Received |
| Jul 13, 2020 | Correspondence Mailed/Faxed/E-mailed |