| Action Date | Action Description |
|---|---|
| Oct 05, 2020 | Maintenance Certification Request |
| Oct 05, 2020 | Administrative Review for Completeness |
| Oct 06, 2020 | Eng Team Review for Completeness |
| Oct 06, 2020 | Application Accepted |
| Oct 06, 2020 | Project Manager |
| Oct 15, 2020 | Engineering Report |
| Oct 15, 2020 | Permit Approved |
| Oct 20, 2020 | HPHC Historical Preservation No Effect |
| Oct 20, 2020 | HPHC Review Pending |
| Nov 02, 2020 | US Army Corps of Engineers Approval Received |