| Action Date | Action Description |
|---|---|
| Jan 31, 2022 | Assent Application Received |
| Feb 01, 2022 | Administrative Review for Completeness |
| Feb 02, 2022 | Bio Team Review for Completeness |
| Feb 02, 2022 | Application Accepted |
| Feb 03, 2022 | Project Manager |
| Feb 25, 2022 | HPHC Review Pending |
| Feb 25, 2022 | HPHC Historical Preservation No Effect |
| Apr 11, 2022 | Additional Information Requested from Applicant |
| Apr 12, 2022 | CHA Worksheet received |
| Apr 22, 2022 | Plans Received |
| Apr 29, 2022 | Biologist Report |
| May 03, 2022 | Typist for Processing |
| May 05, 2022 | Executive Sign Off |
| May 05, 2022 | Sent to Photo Copy |
| May 05, 2022 | Permit Mailed |
| May 05, 2022 | Permit Approved |
| May 05, 2022 | Permit Mailed |
| Jun 03, 2022 | Land Evidence Date |
| Sep 21, 2023 | Modification Request |
| Sep 25, 2023 | Administrative Review for Completeness |
| Sep 26, 2023 | Bio Team Review for Completeness |
| Sep 27, 2023 | Additional Information Received |
| Oct 06, 2023 | HPHC Historical Preservation No Effect |
| Oct 06, 2023 | Biologist Report |
| Oct 10, 2023 | Modification Approved |
| Oct 10, 2023 | Typist for Processing |
| Oct 10, 2023 | Executive Sign Off |
| Oct 10, 2023 | Sent to Photo Copy |
| Oct 12, 2023 | Permit Mailed |
| Oct 24, 2023 | Land Evidence Date |
| Nov 17, 2023 | Note to File |