| Action Date | Action Description |
|---|---|
| Feb 04, 2022 | Assent Application Received |
| Feb 23, 2022 | Administrative Review for Completeness |
| Mar 01, 2022 | Eng Team Review for Completeness |
| Mar 01, 2022 | Bio Team Review for Completeness |
| Mar 01, 2022 | Application Accepted |
| Mar 01, 2022 | Project Manager |
| Mar 09, 2022 | Plans Received |
| Mar 21, 2022 | HPHC Historical Preservation No Effect |
| Mar 21, 2022 | HPHC Review Pending |
| Apr 08, 2022 | Engineering Report |
| Apr 19, 2022 | Typist for Processing |
| Apr 20, 2022 | Permit Mailed |
| Apr 21, 2022 | Permit Approved |
| Apr 21, 2022 | Executive Sign Off |
| Apr 21, 2022 | Sent to Photo Copy |