| Action Date | Action Description |
|---|---|
| Aug 11, 2022 | Assent Application Received |
| Aug 17, 2022 | Administrative Review for Completeness |
| Aug 22, 2022 | Eng Team Review for Completeness |
| Aug 22, 2022 | Application Accepted |
| Aug 24, 2022 | Project Manager |
| Sep 21, 2022 | HPHC Historical Preservation No Effect |
| Oct 04, 2022 | Typist for Processing |
| Oct 04, 2022 | Executive Sign Off |
| Oct 04, 2022 | Sent to Photo Copy |
| Oct 04, 2022 | Permit Approved |
| Oct 04, 2022 | Engineering Report |
| Oct 04, 2022 | Permit Mailed |
| Oct 11, 2022 | Permit Mailed |
| Oct 18, 2022 | Land Evidence Date |