| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 28, 2023 | Assent Application Received |
| Nov 30, 2023 | Administrative Review for Completeness |
| Dec 01, 2023 | Bio Team Review for Completeness |
| Dec 01, 2023 | Project Manager |
| Dec 01, 2023 | Application Accepted |
| Dec 01, 2023 | Category A* (Docks) |
| Dec 18, 2023 | 30 day Public Notice Issued |
| Dec 20, 2023 | HPHC Historical Preservation No Effect |
| Dec 26, 2023 | Objections/Comments Received |
| Jan 18, 2024 | Public Notice End Date |
| Jan 22, 2024 | Objections/Comments Received |
| Feb 18, 2024 | Public Notice End Date Extension Granted |
| Feb 19, 2024 | Comments Received |
| Feb 20, 2024 | Objections/Comments Received |
| Apr 17, 2024 | Additional Information Received |
| Apr 25, 2024 | 30 day Public Notice Issued |
| May 20, 2024 | Comments Received |
| May 24, 2024 | Objections/Comments Received |
| May 25, 2024 | Public Notice End Date |
| Jun 10, 2024 | Additional Information Received |
| Jun 10, 2024 | Semi-Monthly Meeting Date Scheduled |
| Jun 10, 2024 | Objection withdrawal received |
| Jul 08, 2024 | Mail Agenda Notice |
| Jul 09, 2024 | Biologist Report |
| Jul 10, 2024 | Supervisor Biologist SignOff |
| Jul 10, 2024 | Supervisor Engineer SignOff |
| Jul 15, 2024 | Executive Signoff of Staff Reports |
| Jul 23, 2024 | Council Approval Granted |
| Jul 23, 2024 | Semi-Monthly Meeting Date Scheduled |
| Jul 24, 2024 | Stipulation Package from Biologist |
| Sep 12, 2024 | Typist for Processing |
| Sep 12, 2024 | Executive Sign Off |
| Sep 12, 2024 | Permit Approved |
| Sep 16, 2024 | Permit Mailed |
| Sep 30, 2024 | Land Evidence Date |
| Oct 17, 2024 | US Army Corps of Engineers Approval Received |
| Jan 29, 2025 | Legal Response/Decision |