| Action Date | Action Description |
|---|---|
| Feb 21, 2024 | Buffer Zone Management Application Received |
| Feb 27, 2024 | Administrative Review for Completeness |
| Mar 04, 2024 | Bio Team Review for Completeness |
| Mar 04, 2024 | Project Manager |
| Mar 04, 2024 | Application Accepted |
| Mar 20, 2024 | HPHC Historical Preservation No Effect |
| May 31, 2024 | Additional Information Received |
| Jun 12, 2024 | Biologist Report |
| Jun 18, 2024 | Typist for Processing |
| Jun 18, 2024 | Executive Sign Off |
| Jun 18, 2024 | Sent to Photo Copy |
| Jun 18, 2024 | Permit Approved |
| Jun 21, 2024 | Permit Mailed |