| Action Date | Action Description | 
|---|---|
| Jun 18, 2024 | Federal Consistency Review Request | 
| Jul 12, 2024 | Application Accepted | 
| Jul 26, 2024 | 15 day Public Notice Issued | 
| Aug 02, 2024 | Letter of Support for Project | 
| Aug 07, 2024 | Letter of Support for Project | 
| Aug 08, 2024 | Letter of Support for Project | 
| Aug 09, 2024 | Letter of Support for Project | 
| Aug 09, 2024 | Public Notice End Date | 
| Aug 13, 2024 | Objections/Comments Received | 
| Aug 13, 2024 | Additional Information Received | 
| Jan 16, 2025 | Application Cancelled | 
| Jan 16, 2025 | Policy Review |