| Action Date | Action Description |
|---|---|
| Jul 22, 2024 | Maintenance Certification Request |
| Jul 24, 2024 | Administrative Review for Completeness |
| Aug 08, 2024 | Eng Team Review for Completeness |
| Aug 08, 2024 | Deficient Application - Owner Notification Sent |
| Aug 29, 2024 | Plans Received |
| Oct 16, 2024 | Deficiency Response Received |
| Oct 23, 2024 | Bio Team Review for Completeness |
| Oct 23, 2024 | Eng Team Review for Completeness |
| Oct 23, 2024 | Application Accepted |
| Oct 23, 2024 | Project Manager |
| Oct 24, 2024 | Additional Information Received |
| Oct 30, 2024 | HPHC Historical Preservation No Effect |
| Nov 19, 2024 | Engineering Report |
| Nov 27, 2024 | Plans Received |
| Dec 06, 2024 | Typist for Processing |
| Dec 06, 2024 | Biologist Report |
| Dec 10, 2024 | Executive Sign Off |
| Dec 10, 2024 | Sent to Photo Copy |
| Dec 10, 2024 | Permit Approved |
| Dec 11, 2024 | Permit Mailed |
| Dec 31, 2024 | Land Evidence Date |
| Jan 27, 2025 | Commencement of Work Notice received |