| Action Date | Action Description |
|---|---|
| Jan 31, 2025 | Assent Application Received |
| Feb 07, 2025 | Administrative Review for Completeness |
| Feb 13, 2025 | Eng Team Review for Completeness |
| Feb 13, 2025 | Project Manager |
| Feb 13, 2025 | Application Accepted |
| Feb 18, 2025 | Correspondence Received |
| Feb 19, 2025 | Plans Received |
| Mar 06, 2025 | 30 day Public Notice Issued |
| Mar 10, 2025 | US Army Corps of Engineers Project Number received. |
| Mar 11, 2025 | Correspondence Received |
| Mar 20, 2025 | HPHC Historical Preservation No Effect |
| Apr 06, 2025 | Public Notice End Date |
| Apr 25, 2025 | Comments Received |
| Apr 30, 2025 | Public Notice End Date Extension Granted |
| May 05, 2025 | Engineering Report |
| May 09, 2025 | Typist for Processing |
| May 09, 2025 | Executive Sign Off |
| May 09, 2025 | Sent to Photo Copy |
| May 09, 2025 | Permit Approved |
| May 13, 2025 | Permit Mailed |
| Jun 10, 2025 | Land Evidence Date |
| Jul 22, 2025 | Additional Information Received |
| Aug 18, 2025 | US Army Corps of Engineers Approval Received |