| Action Date | Action Description |
|---|---|
| Nov 21, 2005 | Assent Application Received |
| Nov 22, 2005 | Administrative Review for Completeness |
| Nov 22, 2005 | Team Review for Completeness |
| Nov 22, 2005 | Application Accepted |
| Nov 22, 2005 | Category A* (Docks) |
| Dec 06, 2005 | HPHC Historical Preservation No Effect |
| Aug 21, 2006 | 30 day Public Notice Issued |
| Sep 18, 2006 | US Army Corp of Engineers Permit Date |
| Sep 21, 2006 | Public Notice End Date |
| Sep 25, 2006 | US Army Corps of Engineers Approval Received |
| Sep 29, 2006 | Dock Meeting Scheduled (Admin) |
| Sep 29, 2006 | Biologist Report |
| Sep 29, 2006 | Engineering Report |
| Sep 29, 2006 | Land Evidence Date |
| Sep 29, 2006 | Dock sub-committee Approved |
| Oct 02, 2006 | Typist for Processing |
| Oct 03, 2006 | Executive Sign Off |
| Oct 03, 2006 | Sent to Photo Copy |
| Oct 03, 2006 | Permit Approved |
| Jan 02, 2007 | Land Evidence Date |
| Jun 21, 2007 | Commencement of Work Notice received |
| Aug 25, 2008 | Modification Request |
| Aug 28, 2008 | Administrative Review for Completeness |
| Aug 28, 2008 | Team Review for Completeness |
| Aug 28, 2008 | Team Review for Completeness |
| Sep 12, 2008 | HPHC Historical Preservation No Effect |
| Sep 18, 2008 | 30 day Public Notice Issued |
| Oct 14, 2008 | US Army Corp of Engineers Permit Date |
| Oct 14, 2008 | US Army Corps of Engineers Approval Received |
| Oct 14, 2008 | US Army Corp of Engineers Permit Date |
| Oct 14, 2008 | US Army Corps of Engineers Approval Received |
| Oct 18, 2008 | Public Notice End Date |
| Nov 03, 2008 | Dock Meeting -- Approval |
| Nov 05, 2008 | Modification Approved |
| Nov 05, 2008 | Typist for Processing |
| Nov 05, 2008 | Executive Sign Off |
| Nov 05, 2008 | Sent to Photo Copy |
| Nov 05, 2008 | Biologist Report |
| Nov 05, 2008 | Engineering Report |
| Dec 17, 2008 | Land Evidence Date |