| Action Date | Action Description |
|---|---|
| Dec 09, 2005 | Assent Application Received |
| Jan 10, 2006 | Administrative Review for Completeness |
| Feb 01, 2006 | Team Review for Completeness |
| Feb 01, 2006 | Application Accepted |
| Feb 02, 2006 | Category B assigned |
| Feb 08, 2006 | 30 day Public Notice Issued |
| Feb 15, 2006 | HPHC Historical Preservation No Effect |
| Feb 17, 2006 | Correspondence Received |
| Mar 15, 2006 | Correspondence Received |
| Mar 16, 2006 | Engineering Report |
| Mar 17, 2006 | Public Notice End Date |
| Mar 20, 2006 | US Army Corp of Engineers Permit Date |
| Mar 22, 2006 | US Army Corps of Engineers Approval Received |
| Apr 11, 2006 | Biologist Report |
| Jun 05, 2006 | Supervisor Biologist SignOff |
| Jun 05, 2006 | Supervisor Engineer SignOff |
| Jun 06, 2006 | Executive Sign Off |
| Jul 14, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jul 14, 2006 | Mail Agenda Notice |
| Jul 25, 2006 | Semi-Monthly Meeting Postponed |
| Jul 25, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jul 31, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jul 31, 2006 | Mail Agenda Notice |
| Aug 08, 2006 | Semi-Monthly Meeting Held |
| Aug 08, 2006 | Council Approval Granted |
| Aug 08, 2006 | Semi-Monthly Meeting Date Scheduled |
| Aug 11, 2006 | Stipulation Package by Engineer |
| Aug 16, 2006 | Stipulation Package from Biologist |
| Aug 16, 2006 | Typist for Processing |
| Aug 16, 2006 | Executive Sign Off |
| Aug 16, 2006 | Sent to Photo Copy |
| Aug 18, 2006 | Permit Approved |
| Aug 21, 2006 | Land Evidence Date |
| Sep 15, 2006 | Legal Response/Decision |