| Action Date | Action Description |
|---|---|
| Feb 28, 2006 | Assent Application Received |
| Feb 28, 2006 | Administrative Review for Completeness |
| Mar 01, 2006 | Team Review for Completeness |
| Mar 01, 2006 | Application Accepted |
| Mar 20, 2006 | HPHC Historical Preservation No Effect |
| Sep 12, 2006 | Typist for Processing |
| Sep 12, 2006 | Executive Sign Off |
| Sep 12, 2006 | Sent to Photo Copy |
| Sep 12, 2006 | Permit Approved |
| Sep 12, 2006 | Biologist Report |
| Sep 12, 2006 | Engineering Report |
| Sep 26, 2006 | Land Evidence Date |
| Aug 05, 2009 | Extension of Permit Request |
| Sep 10, 2009 | Enforcement Compliance Inspection Required |
| Sep 11, 2009 | Process Extension |
| Sep 11, 2009 | Extension Approved |
| Aug 27, 2010 | Extension of Permit Request |
| Aug 27, 2010 | Enforcement Compliance Inspection Required |
| Aug 27, 2010 | Extension Toll letter mailed |