| Action Date | Action Description |
|---|---|
| Oct 12, 2006 | Assent Application Received |
| Oct 13, 2006 | Administrative Review for Completeness |
| Oct 27, 2006 | Team Review for Completeness |
| Oct 27, 2006 | Application Accepted |
| Nov 02, 2006 | 30 day Public Notice Issued |
| Nov 09, 2006 | HPHC Historical Preservation No Effect |
| Nov 30, 2006 | Correspondence Received |
| Nov 30, 2006 | Correspondence Received |
| Dec 02, 2006 | Public Notice End Date |
| Jan 18, 2007 | Engineering Report |
| Jan 18, 2007 | Geologist Report |
| Jan 29, 2007 | Executive Sign Off |
| Feb 05, 2007 | Scheduled for Section 110 Review meeting |
| Feb 07, 2007 | Dock/1.1.6 Review approval |
| Feb 19, 2007 | Executive Sign Off |
| Feb 19, 2007 | Sent to Photo Copy |
| Feb 19, 2007 | Permit Approved |
| Feb 19, 2007 | Typist for Processing |
| Feb 20, 2007 | Land Evidence Date |
| Mar 16, 2007 | Commencement of Work Notice received |