| Action Date | Action Description |
|---|---|
| Mar 31, 2008 | Assent Application Received |
| Apr 01, 2008 | Administrative Review for Completeness |
| Apr 01, 2008 | Team Review for Completeness |
| Apr 01, 2008 | Team Review for Completeness |
| Apr 01, 2008 | Application Accepted |
| Apr 01, 2008 | Category A* (Docks) |
| May 05, 2008 | HPHC Historical Preservation No Effect |
| May 16, 2008 | Plans Received |
| May 20, 2008 | 30 day Public Notice Issued |
| Jun 20, 2008 | Public Notice End Date |
| Jun 23, 2008 | Dock Meeting Scheduled (Admin) |
| Jun 23, 2008 | Typist for Processing |
| Jun 23, 2008 | Executive Sign Off |
| Jun 23, 2008 | Sent to Photo Copy |
| Jun 23, 2008 | Permit Approved |
| Jun 23, 2008 | Biologist Report |
| Jun 23, 2008 | Engineering Report |
| Jul 09, 2008 | Land Evidence Date |
| Aug 05, 2008 | US Army Corp of Engineers Permit Date |
| Aug 07, 2008 | US Army Corps of Engineers Approval Received |
| Aug 28, 2009 | Modification Request |
| Aug 31, 2009 | Administrative Review for Completeness |
| Aug 31, 2009 | Team Review for Completeness |
| Aug 31, 2009 | Team Review for Completeness |
| Sep 11, 2009 | HPHC Historical Preservation No Effect |
| Feb 19, 2010 | Additional Information Received |
| Feb 24, 2010 | 30 day Public Notice Issued |
| Mar 24, 2010 | Public Notice End Date |
| Apr 05, 2010 | Dock Meeting -- Approval |
| Apr 06, 2010 | Modification Approved |
| Apr 06, 2010 | Biologist Report |
| Apr 06, 2010 | Engineering Report |
| Apr 15, 2010 | US Army Corp of Engineers Permit Date |
| Jun 14, 2010 | Land Evidence Date |
| Oct 07, 2010 | Commencement of Work Notice received |