| Action Date | Action Description | 
|---|---|
| Apr 02, 2008 | Freshwater Wetland - Request to Alter | 
| Apr 02, 2008 | Administrative Review for Completeness | 
| Apr 02, 2008 | Team Review for Completeness | 
| Apr 02, 2008 | Team Review for Completeness | 
| Apr 02, 2008 | Application Accepted | 
| Jun 09, 2008 | 30 day Public Notice Issued | 
| Aug 07, 2008 | Biologist Report | 
| Aug 07, 2008 | Engineering Report | 
| Aug 07, 2008 | Correspondence Received | 
| Aug 08, 2008 | Public Notice End Date | 
| Aug 08, 2008 | Executive Signoff of Staff Reports | 
| Aug 25, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| Aug 25, 2008 | Mail Agenda Notice | 
| Sep 03, 2008 | Continuance Requested | 
| Sep 09, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Jan 30, 2009 | Correspondence Received | 
| Feb 09, 2009 | Correspondence Received | 
| Feb 10, 2009 | Mail Agenda Notice | 
| Feb 10, 2009 | Ready to Schedule Semi-Monthly Meeting | 
| Feb 24, 2009 | Semi-Monthly Meeting Postponed | 
| Feb 24, 2009 | Semi-Monthly Meeting Date Scheduled | 
| Feb 24, 2009 | Mail Agenda Notice | 
| Mar 23, 2009 | US Army Corp of Engineers Permit Date | 
| Mar 24, 2009 | Semi-Monthly Meeting Postponed | 
| Mar 24, 2009 | Semi-Monthly Meeting Date Scheduled | 
| Mar 25, 2009 | US Army Corps of Engineers Approval Received | 
| Mar 26, 2009 | Mail Agenda Notice | 
| Mar 31, 2009 | Mail Agenda Notice | 
| Apr 07, 2009 | Council Approval Granted | 
| Apr 07, 2009 | Semi-Monthly Meeting Date Scheduled | 
| Apr 07, 2009 | Semi-Monthly Meeting Held | 
| May 19, 2009 | Stipulation Package from Biologist | 
| May 19, 2009 | Stipulation Package by Engineer | 
| May 22, 2009 | Typist for Processing | 
| May 22, 2009 | Permit Approved | 
| May 27, 2009 | Executive Sign Off | 
| May 29, 2009 | Sent to Photo Copy | 
| May 29, 2009 | Land Evidence Date | 
| Sep 15, 2009 | Commencement of Work Notice received | 
| Jan 27, 2010 | Legal Response/Decision |