| Action Date | Action Description |
|---|---|
| May 18, 2009 | Assent Application Received |
| May 19, 2009 | Administrative Review for Completeness |
| May 19, 2009 | Team Review for Completeness |
| May 19, 2009 | Team Review for Completeness |
| May 20, 2009 | Deficient Application - Owner Notification Sent |
| Jun 01, 2009 | Deficient Application Picked Up |
| Aug 07, 2009 | Deficiency Response Received |
| Aug 11, 2009 | Team Review for Completeness |
| Aug 11, 2009 | Team Review for Completeness |
| Aug 11, 2009 | Application Accepted |
| Aug 27, 2009 | HPHC Historical Preservation No Effect |
| Oct 05, 2009 | Plans Received |
| Nov 27, 2009 | Additional Information Received |
| Nov 30, 2009 | Typist for Processing |
| Nov 30, 2009 | Permit Approved |
| Nov 30, 2009 | Biologist Report |
| Nov 30, 2009 | Engineering Report |
| Jan 11, 2010 | Land Evidence Date |
| Nov 19, 2012 | Extension Toll letter mailed |
| May 27, 2014 | Extension Toll letter mailed |