| Action Date | Action Description | 
|---|---|
| May 20, 2009 | Assent Application Received | 
| May 21, 2009 | Administrative Review for Completeness | 
| May 21, 2009 | Team Review for Completeness | 
| May 21, 2009 | Team Review for Completeness | 
| May 21, 2009 | Application Accepted | 
| May 26, 2009 | 30 day Public Notice Issued | 
| Jun 23, 2009 | Additional Information Received | 
| Jun 25, 2009 | HPHC Historical Preservation No Effect | 
| Jun 26, 2009 | Public Notice End Date | 
| Jul 22, 2009 | Water Quality Certification | 
| Jul 31, 2009 | Plans Received | 
| Sep 01, 2009 | Biologist Report | 
| Sep 01, 2009 | Engineering Report | 
| Sep 02, 2009 | Supervisor Biologist SignOff | 
| Sep 02, 2009 | Supervisor Engineer SignOff | 
| Sep 03, 2009 | US Army Corp of Engineers Permit Date | 
| Sep 08, 2009 | Executive Signoff of Staff Reports | 
| Sep 10, 2009 | Ready to Schedule Semi-Monthly Meeting | 
| Sep 10, 2009 | Mail Agenda Notice | 
| Sep 10, 2009 | US Army Corps of Engineers Approval Received | 
| Sep 22, 2009 | Semi-Monthly Meeting Date Scheduled | 
| Sep 22, 2009 | Semi-Monthly Meeting Held | 
| Sep 22, 2009 | Council Approval Granted | 
| Sep 24, 2009 | Stipulation Package from Biologist | 
| Sep 24, 2009 | Stipulation Package by Engineer | 
| Sep 24, 2009 | Permit Approved | 
| Nov 09, 2009 | Legal Response/Decision | 
| Oct 24, 2012 | Extension Toll letter mailed | 
| Jan 24, 2018 | Expiration of Assent/End of Tolling Legislation | 
| Mar 01, 2019 | Extension of Permit Request | 
| Mar 07, 2019 | Enforcement Compliance Inspection Required | 
| Mar 07, 2019 | Process Extension | 
| Mar 07, 2019 | Extension Approved | 
| Apr 11, 2019 | Modification Request | 
| Apr 12, 2019 | Administrative Review for Completeness | 
| Apr 25, 2019 | Application Accepted | 
| May 16, 2019 | Biologist Report | 
| May 16, 2019 | Engineering Report | 
| May 16, 2019 | Modification Approved | 
| May 21, 2019 | HPHC Historical Preservation No Effect | 
| May 21, 2019 | HPHC Review Pending | 
| May 23, 2019 | Land Evidence Date | 
| May 01, 2020 | Extension of Permit Request | 
| May 05, 2020 | Enforcement Compliance Inspection Required | 
| May 19, 2020 | Process Extension | 
| May 19, 2020 | Extension Approved | 
| Mar 15, 2021 | Extension of Permit Request | 
| May 11, 2021 | Enforcement Compliance Inspection Required | 
| May 11, 2021 | Extension Approved | 
| Jul 23, 2021 | Commencement of Work Notice received | 
| May 12, 2022 | Phone Call | 
| Aug 17, 2022 | Additional Information Received |