| Action Date | Action Description |
|---|---|
| Sep 15, 2009 | Assent Application Received |
| Sep 16, 2009 | Administrative Review for Completeness |
| Sep 18, 2009 | Team Review for Completeness |
| Sep 18, 2009 | Application Accepted |
| Sep 28, 2009 | 30 day Public Notice Issued |
| Oct 09, 2009 | HPHC Historical Preservation No Effect |
| Oct 22, 2009 | 30 day Public Notice Issued |
| Oct 26, 2009 | Public Notice End Date |
| Nov 19, 2009 | Objections/Comments Received |
| Nov 22, 2009 | Public Notice End Date |
| Dec 22, 2009 | Biologist Report |
| Dec 22, 2009 | Engineering Report |
| Dec 22, 2009 | Executive Signoff of Staff Reports |
| Dec 23, 2009 | Additional Information Received |
| Dec 30, 2009 | Ready to Schedule Semi-Monthly Meeting |
| Dec 30, 2009 | Mail Agenda Notice |
| Jan 13, 2010 | Council Approval Granted |
| Jan 13, 2010 | Semi-Monthly Meeting Date Scheduled |
| Jan 26, 2010 | Stipulation Package from Biologist |
| Jan 26, 2010 | Stipulation Package by Engineer |
| Jan 29, 2010 | Permit Approved |
| Feb 03, 2010 | Land Evidence Date |
| Feb 18, 2010 | Legal Response/Decision |
| Sep 15, 2010 | Modification Request |
| Sep 17, 2010 | Administrative Review for Completeness |
| Sep 17, 2010 | Team Review for Completeness |
| Sep 22, 2010 | Modification Approved |
| Sep 23, 2010 | Team Review for Completeness |
| Sep 24, 2010 | Typist for Processing |
| Sep 24, 2010 | Executive Sign Off |
| Sep 24, 2010 | Sent to Photo Copy |
| Jan 18, 2011 | Duplicate Original Assent requested/mailed |
| Jan 19, 2011 | Land Evidence Date |
| Apr 04, 2012 | Correspondence Received |
| Dec 04, 2012 | Extension Toll letter mailed |