| Action Date | Action Description |
|---|---|
| Aug 30, 2010 | Assent Application Received |
| Aug 31, 2010 | Administrative Review for Completeness |
| Aug 31, 2010 | Team Review for Completeness |
| Aug 31, 2010 | Team Review for Completeness |
| Aug 31, 2010 | Application Accepted |
| Aug 31, 2010 | Engineering Report |
| Aug 31, 2010 | Biologist Report |
| Aug 31, 2010 | Additional Information Received |
| Sep 01, 2010 | Typist for Processing |
| Sep 01, 2010 | Executive Sign Off |
| Sep 01, 2010 | Permit Approved |
| Sep 02, 2010 | Sent to Photo Copy |
| Sep 16, 2010 | HPHC Historical Preservation No Effect |
| Dec 07, 2010 | Land Evidence Date |