| Action Date | Action Description |
|---|---|
| Oct 27, 2010 | Freshwater Wetland - Preliminary Determination |
| Oct 27, 2010 | Administrative Review for Completeness |
| Nov 30, 2010 | Team Review for Completeness |
| Dec 01, 2010 | Team Review for Completeness |
| Dec 03, 2010 | Application Accepted |
| Dec 03, 2010 | Biologist Report |
| Dec 03, 2010 | Typist for Processing |
| Dec 03, 2010 | Permit Approved |
| Dec 07, 2010 | Executive Sign Off |
| Dec 07, 2010 | Sent to Photo Copy |
| Jul 29, 2011 | Freshwater Wetland - Permit Modification Request |
| Aug 01, 2011 | Administrative Review for Completeness |
| Aug 11, 2011 | Modification Approved |
| Aug 15, 2011 | Land Evidence Date |
| Aug 15, 2011 | Typist for Processing |
| Aug 15, 2011 | Executive Sign Off |
| Aug 15, 2011 | Sent to Photo Copy |